The Fosters Construction team have finished off the year strong, with tremendous progress made on site. The crew will be back on site from 8 January 2024, refreshed and ready for another big year.  

 

Progress on site

Highlights from December 2023.

Key activities last month include the following.

  • Laying of the ComFlor (steel deck) across Level 1.

  • Concrete pour to the ComFlor at Level 2 of the heritage building.

  • Completion of foundation rafts.

  • Installation of insulation.

  • Erection of more shear walls.

 

Significant events coming up

The following progress is expected to occur in January 2024.

  • Reinforcing the newly laid ComFlor in readiness for concrete pours.

  • Installation of more of the ComFlor.

  • Erection of structural steel.

 

The Waikato Regional Theatre site this month. Photo: Foster Construction.

Overall Programme

The WRT's construction programme will be reviewed in the New Year and an update issued in due course.

 

Communications

Foster Construction team email for any queries relating to this project - queries.wrt@fosters.co.nz.

 

About this Update…

These Waikato Regional Theatre Construction Updates are produced by Graeme Ward and Georgia Osman from RDT Pacific, the Theatre’s Overall Project Manager, assisted by Mark Servian from Momentum Waikato, their Communications and Marketing Manager.

These newsletter issues are posted at the website waikatoregionaltheatre.co.nz – the dedicated web address for construction news and contacts, separate from Momentum Waikato’s theatre community and fundraising site sharethestage.co.nz.