Waikato Regional Theatre – Overall Construction Timeline

Phase Timing

Site set up and preparation

August 2021 – October 2021

Demolition

November 2021 – July 2022

Earthworks

June – September 2022

Foundations    

August 2022 – February 2023

Structure

December 2022 – May 2023

Envelope

April – August 2023

Fit-out

June 2023 – April 2024

Completion

May – June 2024

Significant Events

Tasks That May Require Lane Closures or Works Outside of Normal Working Hours

  • Site fencing set-up

  • Crane erection and dismantle

  • Removal of existing canopies

  • Hotel façade retention works

  • Large concrete pours

  • Large component delivery

  • Sapper Moore Jones Place reconstruction