Teenaa koutou and welcome to the Paengawhaawhaa-April 2024 edition of the Waikato Regional Theatre Construction Update.
The shorter, colder days are definitely here, but that hasn’t prevented the team from making great progress on site.
Progress on site
Highlights from the last month.
Laying and pouring of the composite flooring (ComFlor) across Level 2 in the commercial space.
Finished pouring the walls around the stage area.
Installation of the roof trusses across the heritage building.
Continued installation of the structural steel across the site.
Clearing of greenery around the upper part of the old staircase down to the riverbank.
Significant events coming up
The following progress is expected to occur in the next month.
Reinforcing and pouring floors in the Theatre.
Progression of the structural steel installation across the site.
Progression of drainage installation across the site.
Ground testing in the riverbank area.
The Theatre site seen from the south-east in mid March 2024.
Overall Programme
The WRT’s construction programme has been updated as follows.
Site Set Up Completed
Demo Completed
Earthworks Completed
Foundations Completed
Structure Commenced - Due for Completion early 2025
Envelope Commenced - Due for Completion mid 2025
Construction Completion Due for Completion 2025
Fit out and Commissioning Due for Completion 2025
Communications
Foster Construction team email for any queries relating to this project - queries.wrt@fosters.co.nz.