Teenaa koutou and welcome to September’s Waikato Regional Theatre Construction Update.
Progress on site continues, including earthworks, heritage basement strengthening activities, demolition and asbestos removal works, with the final few structural components for the façade retention being installed.
The piling works are now well and truly underway – the team are utilising an innovative technology called ‘deep soil mixing’, rather than driving long piles, which would cause a lot of noise and vibration.
The demolition phase continues with the last of the sections soon to be removed at Sapper Moore-Jones Place. Asbestos continues to be found in several locations within the existing structure and is being removed in accordance with the site’s asbestos management plan.
Progress on Site
August saw the achievement of the following works.
Further asbestos removal.
Ongoing demolition.
Completion of shoring of the heritage hotel’s retained level 1 slab.
Completion of ground retention infrastructure installation and start of piling works.
Continuation of Stage 1 excavations.
Completion of façade retention frame, with the final components being installed.
Relocation of Victoria St hoardings to form slip lane.
Continuing construction of heritage basement foundations.
Completion of basement waterproofing.
Significant Events in the Next Month
The following is set to be achieved in September.
Demolition of the northern end of the Hamilton Hotel.
Completion of the Stage 1 excavations.
Completion of the basement propping.
Shotcrete applied to the basement walls.
Removal of the remaining asbestos and contaminated soil.
Completion of new concrete floors, walls and structural steel for heritage basement.
Overall Programme
The project is currently tracking as per dates below, note some amendments to previous editions.
Site set-up August – October 2021
Demolition November 2021 – September 2022
Earthworks June – October 2022
Foundations October 2022 – January 2023
Structure November 2022 – March 2023
Envelope January – April 2023
Fit-out March 2023 – May 2024
Completion June 2024.
Communications
Foster Construction team email for any queries relating to this project - queries.wrt@fosters.co.nz.
About this Update…
These Waikato Regional Theatre Construction Updates are produced by Graeme Ward from RDT Pacific, the Theatre’s Overall Project Manager, assisted by Mark Servian from Momentum Waikato, their Communications and Marketing Manager.
These newsletter issues are posted at the website waikatoregionaltheatre.co.nz – the dedicated web address for construction news and contacts, separate from Momentum Waikato’s theatre community and fundraising site sharethestage.co.nz.